Harringworth Viaduct

Birse Rail - Harringworth Viaduct, Northamptonshire

A project completed before SG4 was introduced

The Challenge

Access to repair/replace a large amount of brickwork damaged by weathering over the course of many years.

The Solution

To purchase a large quantity of new materials and hire in Mabey beams to support our scaffold over the river.  The project was an opportunity to test our Tube-Lock system, which was quick enought to enable us to use just 6 men to complete the project within 3 weeks.

The Outcome

A large scale project completed in record time, whilst ensuring all necessary safety regulations achieved.